Extension of time period for filing defence in view of parallel EPO appeal proceedings

​
Stuart McKellar
​
January 30, 2025

Dainese S.p.A. v. Alpinestars S.p.A., Alpinestars Research S.p.A., Omnia Retail S.r.l., Horizon Moto 95 – Maxxess Cergy, Zund.Stoff Augsburg/Ulrich Herpich E.K., Motocard Bike S.I. (UPC_CFI_472/2024[1])

Decision of 15/01/2025 (ORD_1495/2025)

Background

The claimant lodged an infringement action against the defendants on the basis of two patents, EP3498117 ("EP'117") and EP4072364. Alpinestars S.p.A. ("Defendant 1") had previously opposed EP'117 at the European Patent Office (EPO) and subsequently appealed the rejection of their opposition. These opposition-appeal proceedings were ongoing when the Claimant instigated infringement proceedings.

The normal deadline for filing a defence to an infringement claim, including any counterclaim for revocation, is three months from the service of the claim. Defendant 1 requested an extension of this deadline under Rule 9 RoP, until after the Oral Proceedings in the parallel opposition-appeal.

The original deadline was set to expire on 20/01/2025, with oral proceedings for the opposition-appeal case scheduled for 13/02/2025. Defendant 1 requested an extension until 27/02/2025, i.e. an extension of 38 days in total and 14 days from the conclusion of oral proceedings.

Under Article 33(10) UPCA and Rule 295(a) RoP, the Court may stay proceedings when a "rapid" decision is expected from the EPO in relation to parallel opposition proceedings, including subsequent appeals. Defendant 1 argued that their requested extension would better serve procedural efficiency than such a stay.

The Judge rapporteur invited the other parties to respond to this request. The Claimant requested that that the Court either deny Defendant 1's request, or, if the Court was minded to grant an extension, grant an extension until only 20/02/2025 (i.e. 7 days after the conclusion of oral proceedings). The Claimant argued that Defendant 1 had been aware of the date of oral proceedings in relation to the pending opposition-appeal proceedings since 02/09/2024 but had waited until just before the deadline for filing the statement of defence to request an extension. Additionally, the Claimant argued that if Defendant 1's request was granted then Defendant 1 would be in an advantageous position, not only with respect to the Claimant, but also with respect to the other Defendants.

Decision

The Judge rapporteur ordered that Defendant 1's request be granted and that the deadline be extended until 27/02/2025. The Judge rapporteur held that coordination between appeal proceedings before the EPO and proceedings before the UPC, alongside procedural efficiency, was best served by extending the time limit for filing the defence and counterclaim for revocation. The Judge rapporteur agreed that an extension of 14 days was an appropriate amount of time to consider the opposition-appeal outcome.

Additionally, the Judge rapporteur stated that the other parties may seek a period to submit their observations on the EPO's decision in accordance with Rule 36 RoP. Thus, no party would obtain an unfair advantage.


[1] https://www.unified-patent-court.org/en/node/16547

Recent Case Reports

Court of Appeal affirms interpretation of product-by-process features in claims, and clarifies applicable law pre-June 2023
29 September 2026
The Court of Appeal confirmed that product-by-process features in a product claim limit the claim only where the specified process imparts characteristics that can be achieved solely by that process. It also clarified the law applicable to acts occurring before 1 June 2023, holding that UPC law may apply to ongoing infringement for injunctive relief, whereas damages for acts completed before that date are governed by national law, and that claims for provisional protection remain governed by national law.
Appeal reveals tricky deadlines for orders contained in decisions
29 September 2026
The Court of Appeal held that where a “privileged order” under Rule 220(1)(c), such as an order relating to the production of evidence under Article 59 UPCA and Rule 190 RoP, is contained within a decision on the merits, a 15 day appeal deadline for that order applies, separate from the substantive appeal deadline. Appeals challenging such orders after that deadline are inadmissible, and parties cannot circumvent the appeal rules by re-filing substantially the same request in the appeal proceedings.
Bringing enforcement proceedings while an appeal is still pending risks liability for defendant’s costs
24 September 2026
The Court of Appeal held that setting aside a first-instance decision granting relief subject to recurring penalties generally has retroactive effect. Any penalty fees already paid will be refunded by the Court. The value of proceedings is determined by the interest of the party that brought the action. This is not changed as a result of an appeal. A claimant bringing enforcement proceedings while an appeal is still pending does so at its own risk and may be liable for the defendant’s costs related to the enforcement proceedings.‍